Project is a 113, 000 SF ware house building with car, van, truck parking and loading dock. A portion of the sitework was done by Caruso excavating which included mainly work below subgrade. Diamond was contract to do portions of the site work from subgrade elevation to the surface. Project value is approximately 4M.
Our scope of work included thefollowing:
Installation of stone subbase for the 116K SF building pad
Installation of over 14,000 LF of concrete curb
Installation of over 27K SF of concrete sidewalk
Installation of over 30K tons of DGA Subbase
Installation of over 20K tons of HMA Pavement
Striping
Installations of ADA sign Bollards and DOT signs
Concrete wheel stops
Installation of 2300 SF Retaining Wall
Installation of Ride share and Bus shelter.
Performed miscellaneous site activities as needed for the GC (RC Andersen).
Included an accelerated construction schedule to meet the GCβs timeline.